OGA: New estimates on the cost of UK oil and gas decommissioning

The Oil and Gas Authority (OGA) has published a report which provides a new cost estimate for offshore oil and gas decommissioning in the UK Continental Shelf (UKCS).

With a shared objective of both industry and government to reduce decommissioning costs, the OGA has set industry a target to reduce costs by at least 35%. This report has been produced to provide greater certainty of the cost of decommissioning all of the UK’s current and future offshore facilities, pipelines, development wells, suspended open water exploration wells and appraisal wells and onshore terminals.

The OGA’s approach has been to develop a probabilistic cost estimate, which takes into account the broad range of uncertainties and uses data submitted by oil and gas operators as part of its 2016 UKCS Stewardship Survey. Using this approach, the OGA has produced a decommissioning cost estimate (P50) value of £59.7 billion in 2016 prices. Taking into account the shared goal of a minimum of 35% cost reduction, this results in a target of less than £39 billion.

More     Link

Leave a Reply

Your email address will not be published. Required fields are marked *

I accept that my given data and my IP address is sent to a server in the USA only for the purpose of spam prevention through the Akismet program.More information on Akismet and GDPR.

This site uses Akismet to reduce spam. Learn how your comment data is processed.